College of Marin, Marin County water districts, community leaders and industry professionals are joining forces to bring state-of-the-art water technology practices to county residents. The grand opening of the Water Management and Technology Education Center (WaMTEC) gets underway Thursday, July 19, 11:30 a.m. to 1:00 p.m., on the lawn between the Pomo and Miwok buildings at the Indian Valley Campus. WaMTEC is a public and private partnership comprised of the following founders: College of Marin, North Marin Water District, Marin Municipal Water District, County of Marin Board of Supervisors, Joint Venture Marin, and California Landscape Contractors Association.

back to top

  

District Modernization Update

This summer has been a busy one for College of Marin’s Measure C Bond Modernization Program. The following is a summary of where we are today with specific projects:

Environmental Impact Report (EIR)

The Draft Environmental Impact Reports DEIR for both campuses are undergoing final edits. The reports reflect all comments received at public meetings held on both campuses in May 2007. The reports are a summary of all potential environmental impacts and mitigation measure recommendations for the Bond Spending Implementation Plan.

The DEIR will be delivered to the State Clearinghouse on July 19 to start the 45 day review period. The report will be available on the College website (‘Measure C Updates’ page) and in hard copy on both campuses at the Internet café at IVC and the Kentfield Library. The Swinerton Offices will also have hard copies available for review anytime between 8 a.m. and 5 p.m. Monday through Friday. The Final Environmental Impact Report (FEIR) will be submitted to the Board of Trustees in November for action.

Kentfield Campus

PE Complex Modernization Architect finishing details.

The PE Complex project was submitted to the Division of the State Architect (DSA) on June 15, 2007 for review.

PE Portables Design is in progress for location, set up, utility connections, etc. Our architects are working closely with PE User Group and local agencies to finalize details.

PE Complex PV Project Geotechnical investigation is underway for structural and foundation design. This process is near completion and DSA submittal is expected in late July 2007.

The Larkspur Annex restroom facility should be installed by late August 2007.

Gateway Complex

This past week the project FPP (final project proposal) for the Gateway Complex was submitted to the State to request matching state funds. The review process will take approximately one year.

Science Building Roof Repairs

The current Science Building will be used for “swing space” over the next three to four years. Investigation of the roof is currently in progress and repairs will begin prior to the rainy, winter season.

Science-Math-Central Plant Complex

A new architectural firm has been contracted by the District to complete the design for this project. ED2 International is the new firm. They are underway with concept and programming, picking up where the previous firm left off. ED2 is working closely with the science/math user group and should move into the schematic design phase over the summer break.

West Campus Bridge Project

The bridge project is in its preliminary design phase pending a possible new location based on design changes to the Science-Math-Central Plant Complex. The site location should be resolved before the end of summer.

Performing Arts Modernization

The architects concluded the Schematic Design Phase on June 19, 2007 as scheduled. Currently the architects are refining the cost model. This project will move into the Design Development Phase on July 18, 2007.

New Fine Arts Building

Architects concluded the Schematic Design Phase on June 19, 2007 and are now refining the cost model. This project will move into the Design Development Phase on July 18, 2007.


Indian Valley Campus

New Main Building Complex Building designs were presented to the Board of Trustees for review and comment on June 12, 2007. Schematic design review has been scheduled with DSA this month.

Transportation Technology Complex Building

Building designs were presented to the Board of Trustees for review and comment on June 12, 2007. Schematic design review with DSA occurred on June 22, 2007. The design team is in the process of responding to DSA comments.

back to top

Kudos

Special thanks to Maintenance Supervisor Don Flowers for his initiative in purchasing and his staff for their work installing waterless urinals that will conserve millions of gallons of water.

back to top

Upcoming

 The COM Board of Trustees will hold its regular monthly meeting on July 17, 2007 at 6:30 p.m. in the Staff Lounge, Deedy Student Services, at the Kentfield Campus.

 

College of Marin presents: Free Summer Band Concert on the Lawn

Saturday, July 21, 6:00 p.m. on the lawn in front of the Fine Arts Building on the College of Marin Kentfield campus.  For more information, call the Performing Arts office at: 415.485.9460. 

 

Have a great week!

Frances L. White

Superintendent/President

 

back to top

President's Monday Briefing webpage
Technical Contact: Nicole Cruz, Admin. Assist., 415-485-9648   x7648
Content Responsible: Cathy Summa-Wolfe, Dir. of Communications & Community Relations, 415-485-9528